Phase II By the Numbers

The Phase II project is progressing! These project statistics highlight the massive effort underway!

Manhours

MANHOURS

231,923

Concrete Poured

CONCRETE

POURED

17,602

CUBIC YARDS

Deck Placed 3

DECK

PLACED

210,487

SQUARE FEET

Rebar Placed

REBAR

PLACED

2,186

TONS

Material Hauled

MATERIAL

HAULED

382,480

CUBIC YARDS

Truckloads

TRUCK

LOADS

38,248

Total Length of Trucks

TOTAL LENGTH

OF TRUCKS

(If stacked front to end)

290

MILES

Total Heavy Machinery_1

TOTAL HEAVY 

MACHINERY ONSITE

1,135,000

POUNDS

Shotcrete

SHOTCRETE

APPLIED

167,336

SQUARE FEET

Foundation Piers

FOUNDATION

PIERS

149

Recycled

RECYCLED

MATERIALS

2,235.65

TONS

Excavation Gold

1501 LAVACA

EXCAVATION

Final Depth

65

FEET

Excavation Orange 2

1500 CONGRESS

EXCAVATION

Final Depth

78

FEET

Excavation

TEXAS CAPITOL

MALL EXCAVATION

Final Depth

70

FEET

Master Plan Summary

The Capitol Complex Project will allow the consolidation of staff currently working in leased space. Consolidating staff has the potential to create operational efficiencies between and within agencies, provide visitors easier access to agency offices, and eliminate the cost of leased space for these offices.

Phase I

Phase I of the 2016 Texas Capitol Complex Master Plan was completed in 2022 and included the construction of two new office buildings totaling more than 1 million square feet, 2,000+ above and below ground parking spaces for State employees, a new central utility plant, and three city blocks of the Texas Capitol Mall, a tree-lined promenade located on Congress Avenue between Martin Luther King Jr. Boulevard and 16th Street. The Texas Capitol Mall serves as the northern gateway to the Capitol Complex with public green space for tourism, events, and festivals.

“The 2016 Texas Capitol Complex Master Plan establishes the Capitol Complex as a destination that celebrates the Texas State Capitol with civic spaces, shaded pedestrian-friendly streets, continuous shade and connections to the surrounding community.”

Phase II

Phase II of the Capitol Complex Project includes two additional State office buildings and the final city block of the Texas Capitol Mall and Underground Parking Garage. The first office building will be constructed at 1501 Lavaca, City Block 39. This building will be eight-stories tall and 360,000 gross square feet. The second office building will be constructed at 1500 Congress on City Block 46. This building will be five-stories tall and 165,000 gross square feet. The exteriors will portray a dignified but modern combination of sunset red granite and glass curtain wall bringing healthy natural light into the space. Both buildings will have onsite parking for State employees.

Figure 1

The 2016 Texas Capitol Master Plan re-envisions the Capitol Complex by centralizing all state agencies into a single district united by the Texas Mall.

Figure 2

The Texas Mall is a tree-lined, pedestrian-oriented civic space and cultural gateway to the Capitol Complex.

Figure 3

The master plan identifies potential development throughout the Capitol Complex.

Figure 4

Two new buildings at 1501 Lavaca and 1500 Congress Avenue will be completed as part of Phase II of the master plan.

The Texas Facilities Commission (TFC) is the State agency responsible for implementing Phase One of the master plan. To effectively manage the project, TFC has contracted with Architect of Record, HOK; Construction Manager at Risk, JE Dunn, and Project Controls Manager, Square One to collaborate on this $900 million effort. These firms are providing recommendations on state-of-the-art design and construction practices, and are assisting TFC in preparing conceptual designs and defining a project management plan for the entire Phase II development. As required by the Texas Capitol Complex Master Plan 2020 Update, they are responsible for preparing the conceptual and schematic designs for the new buildings for approval by a compliance panel appointed by the Governor, Lieutenant Governor and Speaker of the House of Representatives. The expert panel will confirm that the designs are in compliance with the principles and guidelines established in the master plan.