Construction Progress Report – 2025 Year in Review

Capitol Complex Phase II Overview December 2025

As we close out 2026, we reflect on the amazing construction effort happening on 15th Street in the Capitol Complex. Please enjoy the photo gallery of progress made by the Capitol Complex Project Phase II Team over the past year.  Thank you to everyone working on this project. March 2025 – Deck pours on the 1500 […]

Phase II of the Capitol Complex Project Tops Out

1501 Lavaca from Northeast corner_August 14, 2025

Phase II of the Capitol Complex Project Tops Out Phase II of the Capitol Complex Project looking southwest. All photos in this article are courtesy of the Texas Facilities Commission. On Friday, August 22, the last steel beam was placed at the highest point on the 1501 Lavaca State Office Building construction. Both the 1500 […]

Capitol Complex Phase II Achieves Temporary Power

Pictured above: Overview of Phase II of the Capitol Complex Project looking east. Photo courtesy of the Texas Facilities Commission. Bringing power to a construction site as large as Phase II of the Capitol Complex Project is not as easy as flipping a switch. There are three phases to powering the project‒generator power, temporary power, […]

Construction Progress Report | May 2025

1501 Lavaca State Office Building Construction May 2025

As we head into the summer months, the Phase II Capitol Complex team is focused on completing each successive level of the two state office buildings and the elevator shafts for the underground parking below the Texas Capitol Mall Extension. Temperatures are starting to rise, so the team has activated heat exhaustion prevention and monitoring […]

Winter Construction on the Capitol Complex Project Phase II

Snowy overview of Phase II on January 20, 2025. (Photos courtesy of TFC and JE Dunn.) Central Texas winters are milder than many parts of the country, however, we still experience freezing temperatures, ice, and snow. Weather events can potentially delay the work schedule, create work hazards, and affect the performance of construction materials. The […]

Construction Progress Updates | February 2025

1501 Lavaca State Office Building The ground level is complete. The project team is currently pouring the first elevated deck. The first level of the building will be completed in March. Utility work on west 15th Street and west 16th Street will continue for a couple of months. 1500 Congress State Office Building The project […]

Deck Pours are Going Full Speed Ahead on Phase II of the Capitol Complex Project

1500 Congress Deck Pour Preparation, January 2025

Deck pours on Phase II of the Capitol Complex Project are ongoing, and if you pass by the construction of the new State office building at 1501 Lavaca, you can now see the construction efforts happening at street level. The photo above shows preparations for a recent concrete deck pour on the 1500 Congress site. […]