Construction Progress Report – November 2023

1501 Lavaca The excavation on all three sites is progressing swiftly, with crews working six days a week from 6 a.m. to 6 p.m. The Lavaca site is nearing the bottom of the excavation, and the loading zone is busy with hauling trucks. Shotcrete and rock anchor installation continues downward. Preparation for the arrival of […]

Sustainability is a Priority on the Capitol Complex Phase II Project

  When the Capitol Complex Phase II Project is complete, two new State office buildings and the fourth block of the Texas Capitol Mall will stand north of the Texas State Capitol. These new additions will help fulfill the overall Capitol Complex Project mandate to consolidate all state agencies within the Capitol Complex, creating the […]

Construction Progress Report – October 2023

As you can see on the progress photos, the excavation on all three sites is progressing swiftly, with crews working six days a week from 6 a.m. to 6 p.m. The Lavaca site is nearing the bottom of the excavation, and the loading zone is busy with hauling trucks. Shotcrete and rock anchor installation continues […]