Safety First on Phase II of the Capitol Complex Project

Trade workers gather for a safety toolbox talk in the early morning hours on the Phase II construction site.

JE Dunn conducts weekly toolbox meetings to help everyone on site keep safety top of mind. The meetings take place in the early pre-dawn hours before work starts and cover a wide range of subjects timely to the current work effort. A recent meeting topic was preventing illness while managing cold temperatures in the morning […]

1501 Lavaca Concrete Pours

Contract Manager-at-Risk JE Dunn continues concrete pours for the basement levels of the 1501 Lavaca State Office Building. The photo above shows all stages of the pouring process, including: 1 Pouring the concrete. 2 Screeding (leveling) with 2x4s and finishing the edge. 3 Floating the concrete with long-handled float tools to push the aggregate down […]

Texas Capitol Mall Slab-on-Grade Vapor Barrier

Yellow vapor barrier, known as Stego Wrap, sealed with red Stego Tape on the Texas Capitol Mall site. The wrap and tape combination creates a water-tight seal between the individual sections. The primary purpose of the vapor barrier is to function as a waterproofing layer, providing protection between the underlying gravel and the concrete slab […]

Lavaca Perimeter Pier Dilling

Beaird Drilling, a JE Dunn team member providing self-performing concrete services, drills perimeter piers around the foundation perimeter of the Lavaca Street office building. The piers will support structural members. The photo shows an A250 drill rig, used to drill each of the six piers to a depth of 120 feet.

Veteran’s Day | 2024

“Our debt to the heroic men and valiant women in the service of our country can never be repaid. They have earned our undying gratitude.”   Harry S. Truman Thank you to all the veterans on the Capitol Complex Project Phase II team and to all who have served. Veterans Working on Phase II of […]

Construction Progress Update | November 2024

Photo above: Construction camera view the Capitol Complex Project Phase II. Work on Phase II of the Capitol Complex Project is humming along. The excavation work is complete and the last major piece of digging equipment has left the site. The excavation reached a depth of sixty-seven feet over two city blocks. The work crews […]

Team Spotlight – Tumlinson Electric, LLC

A Family and A Team Project Role – Electrical Trade Partner Our Team Spotlight series highlights the contributions of the project team members completing the historic Capitol Complex Project Phase II. Pictured Above: Tumlinson Electric team on Phase II of the Capitol Complex Project. Photo courtesy of Tumlinson Electric, LLC Every day, we switch on […]

Pedestrian Updates | November 2024

All sidewalks and crosswalks adjacent to the construction zone are closed.  Crosswalk barriers are in place with arrows pointing to safe sidewalk crossings. Please heed all safety warnings and follow the alternative safe sidewalk routes around the construction zone. Closed Crosswalks and Sidewalks CLOSED: North Side of 15th Street (next to the construction site). Use […]

Neighborhood News | November 2024

Bullock Texas State History Museum A Better Life for Their ChildrenJulius Rosenwald, Booker T. Washington, and the 4,978 Schools that Changed America Exhibit | Closes February 23, 2025 Discover how Rosenwald schools built and uplifted communities, even in the most difficult circumstances.   Born to Jewish immigrants, Julius Rosenwald rose to lead Sears, Roebuck & […]